This autumn, Höganäs Borgestad has performed refractory work at Equinor Mongstad Refinery in Norway for the Turnaround 2019 in a period of 5 weeks. Most of the refractory work was done inside the refinery, which involved the entering of confined spaces. Our services included refractory inspection, wrecking out of old refractory, anchor welding, formwork, refractory gunning, bricklaying, compressing and fiber installations.

Höganäs Borgestad is proud to have managed the greatest refractory workload in decades at Equinor Mongstad Refinery, perfectly balancing workload and safe work behavior. Thanks to our trained and skilled work force, the detailed planning from our HSE (Health, Safety & Environment) and Technical department, the facility know-how and our close cooperation on site with contractors and our customers, the refractory project was completed successfully!

Project in figures:

  • 15,000 man hours
  • Installation team was composed of 50 people (foremen and installers)
  • Management team:
    • Refractory Inspector
    • HSE Manager
    • Installation Supervisor
    • Project Manager
  • 9,600 pcs of anchors were welded
  • 20m3 of old ceramic fibers were replaced with healthier AES fibers from Morgan Advanced Materials
  • 180 tons of refractory material were supplied from our own production facilities in Bjuv, Sweden:
    • Bricks
    • Monolithic
    • Prefabricated Shapes